Lesson 2.1: Tasks

   

 

 

The Tracking toolbar lets you update progress for tasks and track a project’s progress. To enable it, click the View menu, choose Toolbars, and click Tracking.

 

 

Here’s a look at the tracking toolbar:

 

 

View your project’s statistics.

Set the task’s Actual Start date as the scheduled start date. This will also record Actual Duration completed to the current date (or the status date, if one has been specified).

Reschedule work for the current date (or the status date, if one has been specified).

Add a progress line (these will be covered in detail later on).

Set this task as Not Started.

Set this task as 25% complete.

Set this task as 50% complete.

Set this task as 75% complete.

Set this task as 100% complete.

Shows the Update Task form for the selected task.