1. |
Open Microsoft Project
2003. |
|
|
|
|
2. |
Open 3-2 Sample
from the Sample Files folder.
 |
|
|
|
|
3. |
First, let’s set our
status date. Click the
Project menu
and click
Project Information.
 |
|
|
|
|
4. |
Choose
May 15
for the Status Date.
Click
OK.
 |
|
|
|
|
5. |
Click the
View
menu, choose
Table, and click
More Tables.
 |
|
|
|
|
6. |
In the More Tables
dialog, click
Earned Value and click
Apply.
 |
|
|
|
|
7. |
Scroll through the table
and look at the different fields. Note that the fields for the
tasks after the status date have zeroes in them.
 |
|
|
|
|
8. |
Let’s put our Earned
Value data into a more readable form.
Click the
View
menu and click
Reports.
 |
|
|
|
|
9. |
Choose
Costs
and click
Select.
 |
|
|
|
|
10. |
Click
Earned Value
and click
Select.
 |
|
|
|
|
11. |
If you have a printer,
click Print.
If not, just click
Close.
 |
|
|
|
|
12. |
Close the Reports dialog. |
|
|
|
|
13. |
Save your project as 3-2
Completed.
 |
|
|
|
|
14. |
Close Microsoft Project 2003. |