Lesson 3.3: Creating Progress Lines

   

 

 

Here’s a look at a sample progress line:

 

 

Here’s what the line means.

 

Right-facing peaks (circled in orange)

Task is ahead of schedule.

Left-facing peaks (circled in blue)

Task is behind schedule.

Straight line (circled in green)

Task is on schedule.

Tasks untouched by the progress line (circled in red)

Task is in the future and is not affected by the progress line.