SECTION 3
Lesson 3.3: Creating Progress Lines

   

 

 

1.

Open Microsoft Project 2003.

 

 

2.

Open 3-3 Sample from the Sample Files folder.

 

 

 

3.

Someone has added a progress line to our project but it’s not very pretty. Double-click any part of the green line to open the Progress Line dialog.

 

 

 

4.

Click the Dates and Intervals tab.

Uncheck Display selected progress lines.

 

 

 

5.

Check Always display current progress line.

Choose At project status date.

 

 

 

6.

Click the Line Styles tab.

Style your line any way you want.

Click OK.

 

 

 

7.

Save your project as 3-3 Completed.

 

 

 

8.

Close Microsoft Project 2003.