SECTION 3
Lesson 3.4: Tracking a Project’s Progress With the Project Guide

   

 

 

From the sample above, you can see that our task form has changed. A Status Indicator column has been added. Here’s what each of the icons in that column means.

 

Task is complete.

Task is not complete, but all scheduled work has been completed by the status date

All scheduled work has not been completed by the status date.

 

If the field is blank, it means the task isn’t scheduled to start until after the status date.