1. |
Split into
groups and make a list of tasks that will need to be
accomplished for writing our annual report. (If you need help,
refer to the handout in the sample files folder.)
 |
|
|
|
|
2. |
Open
Microsoft Project 2003. This will automatically open a blank
project. |
|
|
|
|
3. |
Click the
Project
menu and click Project
Information.
 |
|
|
|
|
4. |
In the
Project Information dialog, choose
January 1, 2006
for your project start date.
Set the
Schedule from date from the
Project Start Date.
Set the
Current date to January 1,
2006.
Set the
Status date as March 1, 2006.
Click
OK.

|
|
|
|
|
5. |
Click the
Tools
menu and click Change Working
Time.
 |
|
|
|
|
6. |
Click
M
to select the column of Mondays.
 |
|
|
|
|
7. |
On
the right hand side, choose
Nonworking time.
 |
|
|
|
|
8. |
Use the
scroll bar
to scroll to the next month. Click
February 10, 2006.
 |
|
|
|
|
9. |
Delete the
second row of figures,
so you are only working from 8 am to 12 pm.
 |
|
|
|
|
10. |
Click
OK
in the Change Working Time dialog. |
|
|
|
|
11. |
Save
your project as 2-1 Completed. |
|
|
|
|
12. |
Close
Microsoft Project 2003. |