1. |
Open
Microsoft Project 2003. |
|
|
|
|
2. |
Open
2-1 Completed from the Sample Files folder, or
open your saved copy. |
|
|
|
|
3. |
Enter the
following tasks and durations.
 |
|
|
|
|
4. |
Change the
start date
for Task #2 to April 1, 2006.
 |
|
|
|
|
5. |
Project will
prompt you that this is a nonworking date; choose to
change it to the next working day.
 |
|
|
|
|
6. |
Select
task #4
and drag
it up so it becomes task #3.
 |
|
|
|
|
7. |
We
forgot an important task! Click to place your cursor in the
first task.
Then, click
the Insert
menu and click New
Task.
 |
|
|
|
|
8. |
Name the new
task Create introduction and conclusion. Set the duration
to 5 days.
 |
|
|
|
|
9. |
Save
your project as 2-2 Completed. |
|
|
|
|
10. |
Close
Microsoft Project 2003. |