SECTION 2
Lesson 2.3: Editing Tasks

   

 

 

We’re going to take a closer look at the Advanced tab; it contains the settings for task types. You should change this setting whenever possible to maximize Project’s scheduling capabilities.

 

 

Let’s define some of the terms that are used when discussing task types.

 

Duration

This is how long the task will last.

Work

The labour needed to complete the task.

Units

If a resource is needed to complete the task, how much will be required.

Effort-driven

These types of tasks will be completed by people.

Material driven

These types of tasks will be completed by resources.

 

Here’s an overview of the three task types.

 

Task Type

Explanation

If you change…

Project recalculates…

Effort or material driven

Fixed duration

Duration for these tasks will not change.

Units

Work

Either

 

 

Duration

Work

 

 

 

Work

Units

 

Fixed units (default task type)

This task’s units will remain constant.

Units

Duration

Either

 

 

Duration

Work

 

 

 

Work

Duration

 

Fixed Work

This task’s work will remain constant.

Units

Duration

Effort driven

 

 

Duration

Units

 

 

 

Work

Duration

 

 

These types are based on the simple Project scheduling formula: duration times units equals work, or work divided by assignment units equals duration. Here’s an example: it will take 100 hours to complete a house.

 

Duration=100 hours

Units=         1 man

Work= 100 hours

 

But, if we add three men, the equation changes.

 

Work=100 hours

Units=4

Duration= 25 hours                  

 

Task types sound really confusing, but once you start using them they’re easy to understand.