1. |
Open Microsoft
Project 2003. |
|
|
|
|
2. |
Open 2-2
Completed from the sample files folder, or open your saved
copy. |
|
|
|
|
3. |
Create
three new tasks.
 |
|
|
|
|
4. |
Move the last three tasks up
above Task #4. (Remember that you can select multiple tasks by
holding the Ctrl key, and then dragging them to their new home.)
 |
|
|
|
|
5. |
Now,
select tasks five, six,
and seven.
 |
|
|
|
|
6. |
Click the
Indent
button ( ) on the
formatting toolbar to make them subtasks.
 |
|
|
|
|
7. |
At the bottom of
the task list,
create a new task
called Print Report. Then,
double-click
it to open the task information dialog. |
|
|
|
|
8. |
On the
Advanced
tab of the Task Information dialog, check
Mark task as milestone.
For the task type,
choose Fixed
Duration.
Set the duration as
4.5 hours.
 |
|
|
|
|
9. |
Ensure your cursor
is at the bottom
of the task list.
Click the
Insert
menu and click
Recurring Task.
 |
|
|
|
|
10. |
For the task name,
type Check status of CEO Letter.
Set the duration as
30 minutes.
Set the recurrence
as weekly,
on any day you like.
Leave the rest of
the options as the default and click
OK.
 |
|
|
|
|
11. |
Save
your project as 2-3 Completed. |
|
|
|
|
12. |
Close
Microsoft Project 2003. |