Name |
Description |
Type |
|
As Soon As Possible
(ASAP) |
All tasks
start as soon as possible if you asked Project to schedule from
the start date. |
Flexible |
|
As Late As Possible
(ALAP) |
All tasks
start as late as possible if you asked Project to schedule from
the end date. |
Flexible |
|
Start No Earlier
Than (SNET) |
Specifies
the earliest possible date that this task can start. |
Flexible |
|
Finish No Earlier
Than (FNET) |
Specifies
the earliest possible date that this task can finish. |
Flexible |
|
Start No Later Than
(SNLT) |
Specifies
the latest possible date that this task can start. |
Flexible |
|
Finish No Later
Than (FNLT) |
Specifies
the latest possible date that this task can finish. |
Flexible |
|
Must Start On (MSO) |
Specifies
the date that this task must start on. |
Inflexible |
|
Must Finish On
(MFO) |
Specifies
the date that this task must finish. |
Inflexible |