Constraints and
deadlines may seem similar, but they’re used for very different purpose.
Here’s a summary of how they differ.
|
Constraints… |
Deadlines… |
|
Affect how
Project schedules time and resources, sometimes limiting it |
Do not
affect Project’s scheduling |
|
Have
multiple types |
Have limited
settings |
|
Can be
updated at any time |
Can be
updated at any time |
|
Only certain
types can be applied to summary tasks |
Can always
be applied to summary tasks |
In general, it’s
best to limit the constraints that you have so you don’t limit Project’s
scheduling capabilities. |