1. |
Open
Microsoft Project 2003. |
|
|
|
|
2. |
Open
2-4 Completed from the Sample Files folder, or open your
saved copy. |
|
|
|
|
3. |
Let’s create
a calendar for our auditor. Click the
Tools
menu and click Change Working
Time.
 |
|
|
|
|
4. |
In the
Change Working Time dialog, click
New.
 |
|
|
|
|
5. |
Name the
calendar Auditor.
Choose to
make a copy of the Night
Shift calendar.
Click
OK.
 |
|
|
|
|
6. |
Select the
Sunday,
Monday,
Friday,
and Saturday
columns by holding Ctrl and clicking the letter of the day.
Set these
days to Nonworking time.
 |
|
|
|
|
7. |
Select
Tuesday,
Wednesday,
and Thursday
by holding Ctrl and clicking the letter of the day.
Set these
days to a Nondefault working
time of 6pm to
10 pm.
Click
OK.
 |
|
|
|
|
8. |
Click the
View
menu and click Calendar.
 |
|
|
|
|
9. |
Click the
View
menu and click Gantt Chart.
 |
|
|
|
|
10 |
Click the
Format
menu and click Timescale.
 |
|
|
|
|
11. |
By default,
the Middle Tier
tab should be shown.
Choose
Days
as the unit for this tab.
Choose to
show only the middle tier.
Click
OK.
 |
|
|
|
|
12. |
Save
your project as 3-1 Completed. |
|
|
|
|
13. |
Close
Microsoft Project 2003. |