1. |
Open Microsoft Project 2003. |
|
|
|
|
2. |
Open 3-1 Sample from the Sample
Files folder. |
|
|
|
|
3. |
Select tasks 1,
15, and
18.
Click the Edit
menu and click Link Tasks.

|
|
|
|
|
4. |
Open Annual General Meeting from the
Sample Files folder. |
|
|
|
|
5. |
Click the
Window menu and click
Arrange All.

|
|
|
|
|
6. |
Double-click Task
14 to open the Task Information dialog. |
|
|
|
|
7. |
Click the
Predecessors tab.
In the ID field, type Annual General
Meeting\1.
Click OK.

|
|
|
|
|
8. |
In the Annual General Meeting project,
tasks 5 and 6 are linked.
Open the Task Information dialog for
Task 6. |
|
|
|
|
9. |
Click the
Predecessors tab.
Enter a lag time of 1mo.
Click OK.

|
|
|
|
|
10. |
Save the
main project as 3-2 Completed.
Save the
Annual General Meeting project as 3-2 Completed Part 2. |
|
|
|
|
11. |
Close
Microsoft Project 2003. |