1. |
Open Microsoft Project 2003. |
|
|
|
|
2. |
Open 3-3 Sample from the Sample
Files folder. |
|
|
|
|
3. |
Double-click Task
#2 to open the Task Information. |
|
|
|
|
4. |
Click the General
tab.
Type 100 for Percent Complete.
Click OK.

|
|
|
|
|
5. |
Next, click the
View menu and click Task Usage.
 |
|
|
|
|
6. |
Double-click Shawn
Greer.

|
|
|
|
|
7. |
On the
General tab, set his work contour
as Bell.

|
|
|
|
|
8. |
On the Tracking
tab, set Work Complete to 50%.
Click OK.

|
|
|
|
|
9. |
Notice the contour indicator next to this
resource.

|
|
|
|
|
10. |
Save your
project as 3-3 Completed. |
|
|
|
|
11. |
Close
Microsoft Project 2003. |